ROI Guide: Medium Factories

Solar ROI for Medium Factories (150–500kW): The Business Case

The 150-500kW range is the sweet spot for UK industrial solar. Large enough for G99 to be routine, small enough for full AIA coverage, and generating savings of £40,000-£140,000 per year. Here is the complete ROI analysis.

Quick Answer: Medium Factory Solar ROI

A 300kW solar system for a medium manufacturer typically costs £195,000–£270,000 installed. Annual savings of £70,000–£95,000 at 2026 rates give a payback period of 2.5–4 years. This is the sweet spot for UK industrial solar — large enough for G99 connection to be straightforward, small enough for the AIA £1M cap to cover the full installation in a single tax year.

Medium Factory Solar: Complete Cost and ROI Table 2026

Figures based on 2026 installed costs, 28p/kWh electricity rate, 88% self-consumption, 900 kWh/kWp/year generation, and 25% corporation tax for AIA calculation.

Size Installed Cost Annual Generation Annual Savings (28p) AIA Tax Saving After-Tax Cost Payback
150kW £100,000–£135,000 135,000 kWh £37,800 £25,000–£33,750 £75,000–£101,250 2.5–3.5 yrs
200kW £132,000–£180,000 180,000 kWh £50,400 £33,000–£45,000 £99,000–£135,000 2.5–3.5 yrs
300kW (sweet spot) £195,000–£270,000 270,000 kWh £75,600 £48,750–£67,500 £146,250–£202,500 2.5–4 yrs
400kW £255,000–£350,000 360,000 kWh £100,800 £63,750–£87,500 £191,250–£262,500 2.5–3.5 yrs
500kW £315,000–£425,000 450,000 kWh £126,000 £78,750–£106,250 £236,250–£318,750 2.5–3.5 yrs

AIA Note for 400-500kW systems: At £300,000-£425,000 installed cost, the full system cost falls below the annual AIA cap of £1,000,000 and qualifies for 100% first-year deduction in a single tax year. For companies with annual taxable profit below the AIA threshold, phasing across two tax years is recommended to maximise the benefit.

G99 Grid Connection: What Medium Factory Owners Need to Know

All systems in the 150-500kW range require G99 connection. While this adds some time and cost versus the simplified G98 process, it is routine and well-managed by experienced industrial solar installers.

Typical G99 Process Timeline

Week 1
G99 Pre-application Enquiry

Installer submits enquiry to DNO with basic site details. DNO provides initial feasibility feedback within 5 working days.

Week 2-3
Formal G99 Application Submission

Full application submitted with equipment schedules, site drawings, protection relay scheme, and fee payment (typically £150-£800).

Week 4-12
DNO Technical Assessment

DNO reviews application, conducts load flow studies, and issues Technical Acceptance Certificate (TAC). Timeline varies by DNO and local grid capacity.

Week 13-16
Installation and Commissioning

Physical installation proceeds (2-4 weeks for 300kW system). Post-commissioning G99 notification and energisation by DNO.

G99 Costs for 150-500kW Systems

Cost Item Typical Cost
G99 Application Fee £150–£800
Protection Relay Equipment £800–£2,500
DNO Infrastructure (if required) £0–£15,000
Smart Meter Upgrade £200–£600
Typical Total G99 Costs £2,000–£8,000
DNO infrastructure costs can be higher in areas with constrained grid capacity. Your installer should check available export headroom before finalising the specification.

How to Accelerate the G99 Process

1
Submit G99 Early

Submit the application at project inception — not after panels are ordered. The DNO clock starts on receipt.

2
Use an Experienced Installer

Installers with established DNO relationships and complete application submissions avoid common rejection delays.

3
Consider Export Limiting

Agreeing to limit export to grid can speed DNO approval by removing the need for infrastructure upgrades in constrained areas.

The Three-Phase Advantage for Medium Factories

Medium factories with three-phase electrical supplies enjoy significant advantages when installing solar in the 150-500kW range. Understanding your supply configuration helps optimise system design.

Three-Phase Benefits for Solar

  • ✓ Allows balanced load distribution across all three phases
  • ✓ Supports multiple string inverters for redundancy and performance monitoring
  • ✓ Enables larger total system capacity within standard DNO connection parameters
  • ✓ Compatible with three-phase machinery — no phase imbalance issues
  • ✓ Better grid stability and voltage management at point of connection

Inverter Configuration Options

For a 300kW three-phase system, common configurations include:

  • ● 3 × 100kW string inverters — balanced, individual phase control, good redundancy
  • ● 1 × 300kW central inverter — lower cost, slightly reduced redundancy
  • ● 6 × 50kW string inverters — maximum redundancy, more complex monitoring

Your installer should recommend the optimal configuration based on your roof layout, shading profile, and operational requirements.

No IETF Grant: Plan on Tax Relief and Self-Consumption

The Industrial Energy Transformation Fund (IETF) closed in July 2025 with no successor fund planned; its last competition window shut in April 2024. Any payback figure for a medium-sized factory system that assumes an IETF grant is out of date.

For a 150kW to 500kW system the case rests on tax relief (the Annual Investment Allowance gives 100% first-year relief on the first £1 million of qualifying spend), the share of generation the site uses itself, and Smart Export Guarantee income on the surplus.

ROI Sensitivity Analysis: What If Electricity Prices Change?

A well-designed solar ROI analysis should test how returns change under different electricity price scenarios. Here is the sensitivity analysis for a 300kW system with £220,000 installed cost.

Electricity Price Annual Savings Simple Payback After-Tax Payback 25-Year Lifetime Savings
22p/kWh (-10%) £59,400 3.7 years 2.8 years £1,175,000
28p/kWh (base case) £75,600 2.9 years 2.2 years £1,490,000
32p/kWh (+10%) £86,400 2.5 years 1.9 years £1,700,000
38p/kWh (+25%) £102,600 2.1 years 1.6 years £2,010,000

Key finding: Even at electricity prices 10% below current rates, the 300kW system still pays back in under 4 years (3.7 years simple, 2.8 years after-tax). The downside scenario remains very attractive. If electricity prices remain elevated or increase — which most energy market forecasts suggest is more likely than sustained reduction — returns are substantially better than the base case.

Frequently Asked Questions

What is the ideal solar system size for a medium factory? ▼

For medium factories spending £200,000-£500,000/year on electricity, the ideal system size is typically 250-400kW. This range maximises the benefit of three-phase connection capacity, falls well within the AIA £1 million annual limit, and generates enough savings (typically £60,000-£110,000/year) to achieve payback in under 4 years. The 300kW system is the most commonly specified size for medium UK manufacturing sites.

Does G99 add significant cost to a 300kW system? ▼

No. G99 adds relatively modest cost to a 300kW installation — typically £2,000-£8,000 for the connection application, protection relay equipment, and any DNO-required infrastructure upgrades. Against an installation cost of £195,000-£270,000, this represents less than 3-4% of total project cost. The primary impact of G99 is time: allow 8-16 weeks for DNO approval on a 300kW three-phase system.

Can I phase a medium factory solar installation? ▼

Yes, and phasing can be financially advantageous for two reasons. First, if your annual taxable profit is less than £1 million, phasing across two tax years allows you to claim full AIA on each phase. Second, phasing allows you to assess actual generation and self-consumption data from Phase 1 before committing to the full system design of Phase 2. Typical phasing: 150-200kW in Year 1, then expand to 350-500kW in Year 2 once performance data confirms the investment case.

What grants are available for 300kW solar systems? ▼

Not through the IETF: the Industrial Energy Transformation Fund closed in July 2025 with no successor fund planned. A medium-sized manufacturer's support is tax relief — the Annual Investment Allowance gives 100% first-year relief on the first £1 million of qualifying spend — plus Smart Export Guarantee income on surplus power. Check with your accountant how it applies to your tax position.

How long does G99 take for a 200kW system? ▼

G99 approval for a 200kW system typically takes 8-16 weeks from application submission to receiving the Technical Acceptance Certificate from the DNO. The timeline varies by DNO (National Grid Electricity Distribution, UK Power Networks, Northern Powergrid, SP Energy Networks, and Electricity North West all have different process timelines). Applications submitted in Q4 can experience longer times due to DNO workload. Your installer should submit the G99 application at the start of the project, not at the end, to avoid delays to your installation programme.

Send Your Site Details

Send your site details and we reply by email. An enquiry carries no obligation.

Send your site details

Tell us about your factory and we reply by email. A quote request carries no obligation.