Enterprise Solar: Large Industrial Sites

Solar ROI for Large Industrial Sites (500kW–2MW): Enterprise Analysis

Large-scale industrial solar delivers exceptional returns. A 1MW installation pays back in 2.5-4 years and generates £5-7M in lifetime savings over 25 years. Here is the complete enterprise analysis including G99/G100, AIA phasing strategy, and NPV modelling.

Quick Answer: Large Site Solar ROI

A 1MW solar installation on a large industrial site costs £620,000–£850,000 installed. Annual savings of £210,000–£280,000 at 2026 rates give a payback period of 2.5–4 years. Large sites also unlock G100 grid connection options for complex sites and Power Purchase Agreements as an alternative to full capital outlay when preferred by the board. The IETF grant that once served this tier closed in July 2025 with no successor.

Large Industrial Solar: Complete Cost and ROI Table 2026

Figures based on 2026 installed costs at £620-£700/kWp, 28p/kWh electricity rate, 85% self-consumption, 900 kWh/kWp/year. AIA note: systems over £1M benefit from phasing across tax years.

Size Installed Cost Annual Generation Annual Savings (28p) AIA Tax Saving After-Tax Cost Payback
500kW £315,000–£425,000 450,000 kWh £107,100 £78,750–£106,250 £236,250–£318,750 2.5–3 yrs
750kW £472,500–£637,500 675,000 kWh £160,650 £118,125–£159,375 £354,375–£478,125 2.5–3 yrs
1MW (enterprise) £620,000–£850,000 900,000 kWh £214,200 £155,000–£212,500 (*phasing recommended) £465,000–£637,500 2.5–3.5 yrs
1.5MW £930,000–£1,275,000 1,350,000 kWh £321,300 £232,500–£318,750 (*phasing required) £697,500–£956,250 2.5–4 yrs
2MW £1,240,000–£1,700,000 1,800,000 kWh £428,400 £310,000–£425,000 (*multi-year phasing) £930,000–£1,275,000 2.5–4 yrs

AIA Note: The £1M annual AIA limit means 1MW+ systems should be phased across tax years for maximum tax efficiency. Annual savings of £50,000-£100,000+ from the first phase can partially fund subsequent phases, improving the overall project IRR.

G99 vs G100: Understanding the Difference for Large Sites

Both G99 and G100 are engineering recommendations for connecting embedded generation to the UK distribution network. For large industrial sites, understanding which applies is critical for project planning.

G99: Standard Large-Scale Connection

G99 applies to most embedded generation projects in the UK. For large industrial solar:

  • ✓ Applies to most 500kW-1MW installations
  • ✓ Formal DNO application with technical documentation
  • ✓ Protection relay scheme required
  • ✓ Smart Export Management may be required if export capacity is limited
  • ✓ Typical approval timeline: 12-24 weeks at this scale

G100: Enhanced Smart Connection

G100 represents the enhanced smart connection standard, applicable in specific circumstances:

  • ● Applied by some DNOs for systems over 1MW connected to lower-voltage networks
  • ● Requires additional smart management system with DNO-controlled demand response capability
  • ● DNO can remotely reduce export during grid stress events
  • ● Higher connection costs but may enable connections where G99 capacity is unavailable
  • ● Emerging standard — check with your specific DNO for current policies

DNO Constraints and How to Navigate Them

Large systems in congested grid areas may face export constraints. Here are the primary constraint types and mitigation strategies:

Export Limiting

DNO limits export to grid to protect local network. Mitigation: size system for high self-consumption to minimise the financial impact of export limits.

Voltage Rise Issues

Large solar export can cause voltage rise on local network. Mitigation: reactive power management via inverter settings; consider battery storage to reduce peak export.

Grid Reinforcement Costs

DNO may require you to fund local grid reinforcement. Mitigation: pre-application DNO capacity check; consider accepting export limitation to avoid reinforcement costs.

AIA Phasing Strategy for Large Solar Sites

For systems with total installed cost exceeding £1M, strategic phasing across tax years is essential to maximise the Annual Investment Allowance benefit. Here is how to structure it optimally.

Example: 1.5MW System (£1,100,000 installed cost) — 25% Corp Tax Payer

Without Phasing (Single Year)

Total system cost£1,100,000
AIA claimed (limited to £1M)£1,000,000
Balance (£100k) at 18% WDA£18,000
Total Year 1 tax saving£268,000

With Phasing (Two Tax Years)

Phase 1 cost (Year 1)£600,000
Phase 2 cost (Year 2)£500,000
AIA claimed both years (full)£1,100,000
Total tax saving (both years)£275,000
Additional tax benefit from phasing £7,000

On top of the tax saving, phasing provides operational data from Phase 1 to optimise Phase 2 design, and spreads cash flow across two financial years.

No IETF Grant: Plan on Tax Relief and Self-Consumption

The Industrial Energy Transformation Fund (IETF) closed in July 2025 with no successor fund planned; its last competition window shut in April 2024. Any payback figure for a large industrial system that assumes an IETF grant is out of date.

For a 500kW to 2MW system the case rests on three things: tax relief (the Annual Investment Allowance on the first £1 million of qualifying spend, then the 50% first-year allowance, phased across tax years where that helps), the share of generation the site uses itself, and Smart Export Guarantee income or a PPA for the remainder.

25-Year NPV Modelling: 1MW System at Different Discount Rates

For capital allocation decisions in large organisations, Net Present Value (NPV) analysis provides a more rigorous assessment than simple payback. Here is the NPV modelling for a 1MW system (£730,000 installed cost, after-tax £548,000) across three discount rates.

Discount Rate Rationale Year 5 NPV Year 10 NPV Year 25 NPV IRR
6% discount Low-risk capital allocation, typical for ESG-committed companies £355,000 £970,000 £2,290,000 32%
8% discount Standard corporate hurdle rate for many UK manufacturers £288,000 £795,000 £1,720,000 32%
10% discount Higher hurdle rate for risk-adjusted capital allocation £224,000 £593,000 £1,238,000 32%

Key finding: Across all three discount rates, the 1MW solar investment generates strongly positive NPV by Year 10. The IRR of approximately 32% significantly exceeds typical corporate hurdle rates of 8-12%, making this one of the most attractive capital investments available to large manufacturers. Assumptions: 28p/kWh electricity (with 2% annual escalation), 900 kWh/kWp generation, 0.5% annual system degradation, 25-year panel warranty.

Phased Installation: The Preferred Approach for Large Sites

Most large industrial sites above 500kW benefit from a phased installation approach. Here is why and how to structure it effectively.

Year 1

Phase 1: 500-700kW

  • ✓ Install best-performing roof sections first (south-facing, minimal shading)
  • ✓ Establish actual self-consumption baseline
  • ✓ Claim AIA on Phase 1 cost in Tax Year 1
  • ✓ Begin generating £120,000-£165,000/year savings
Year 2

Phase 2: Expand to Full Capacity

  • ✓ Use Phase 1 data to optimise Phase 2 specifications
  • ✓ Add battery storage if self-consumption data supports it
  • ✓ Claim AIA on Phase 2 cost in Tax Year 2
  • ✓ Phase 1 savings partially fund Phase 2 capex
Year 3+

Optimisation Phase

  • ✓ EV charging infrastructure powered by solar
  • ✓ Demand-side management to maximise self-consumption
  • ✓ Battery storage optimisation and flexibility market revenue
  • ✓ Full ISO 50001 and carbon reporting integration

Frequently Asked Questions

Does a 1MW solar system need G100? ▼

Not necessarily. G100 is an enhanced G99 application route used for larger or more complex embedded generation projects, typically above 1MW total capacity or where the connection requires enhanced network management. Some DNOs apply G100 thresholds at different capacity points. For a 1MW system, G99 is most commonly the applicable standard. G100 applies when the system has enhanced smart functions or is connected to a higher-voltage network. Your installer will confirm which standard applies based on your specific DNO's current policies.

Can I claim AIA on a £1M+ solar system? ▼

Yes, but strategy matters. The Annual Investment Allowance (AIA) cap is £1,000,000 per year per business. A £1.2M solar system can be spread across two tax years to claim full AIA on both tranches. Phase 1 (e.g., 600kW at £420,000) is installed and claimed in Tax Year 1; Phase 2 (e.g., 600kW at £420,000) is installed and claimed in Tax Year 2. The combined AIA tax saving for a 25% taxpayer is £210,000 — claimed over two years. Careful planning with your tax advisor is essential to maximise this benefit.

Is there an IETF grant for large industrial sites in 2026? ▼

No. The Industrial Energy Transformation Fund (IETF) closed in July 2025 with no successor fund planned, so there is no IETF grant to apply for. A large site's case rests on tax relief (the Annual Investment Allowance on the first £1 million of qualifying spend, then the 50% first-year allowance), self-consumed power and Smart Export Guarantee income, or a PPA that avoids the capital outlay.

What is the typical G99/G100 process for a 500kW+ system? ▼

For 500kW+ systems, the G99 process involves: (1) Pre-application enquiry to the DNO to check available export headroom (2-4 weeks); (2) Formal G99 application with full electrical drawings, protection relay scheme, and equipment schedules (4-8 weeks for DNO assessment at this scale); (3) Technical Acceptance Certificate issued by DNO; (4) Physical installation (4-8 weeks for 1MW+ system); (5) Post-commissioning DNO witness testing and energisation. Total timeline from project start to energisation is typically 16-28 weeks. Starting the G99 process on day one of project inception is essential.

Should a large site phase solar installation? ▼

Yes, for most sites over 500kW, phasing is recommended for three reasons. First, AIA tax optimisation: phasing across tax years allows full AIA on each phase if total cost exceeds £1M. Second, operational learning: Phase 1 data reveals actual self-consumption rates and optimal inverter configurations before committing to full Phase 2 design. Third, cash flow management: phasing spreads capital expenditure and allows Phase 1 savings to partially fund Phase 2 investment. A typical phasing strategy is 500-700kW in Year 1, expanding to full capacity in Year 2-3.

Send Your Site Details

Send your site details and we reply by email. An enquiry carries no obligation.

Send your site details

Tell us about your factory and we reply by email. A quote request carries no obligation.