UK Factory Solar Specialists
Policy & Funding 12 April 2026 7 min read

Factory Solar Spring 2026: UK Policy and Funding Update

The UK policy landscape for factory solar is busier than at any point since the Feed-in Tariff era. Spring 2026 brings confirmed AIA rates, an open IETF Phase 4 application window, an approaching ESOS deadline and an important EPC update for commercial landlords. This article summarises everything factory owners and energy managers need to know, updated as of April 2026.

Annual Investment Allowance: Still 100% Up to £1 Million

AIA Status: Confirmed for 2026-27

The Annual Investment Allowance (AIA) remains at £1 million per annum for the 2026-27 tax year, as confirmed in the Spring 2026 Budget. Solar panels installed on UK commercial and industrial premises qualify as plant and machinery and are eligible for 100% first-year tax deduction under AIA.

The AIA allows qualifying businesses to deduct the full cost of plant and machinery investments from their taxable profits in the year of purchase, rather than spreading the deduction over multiple years under the standard writing-down allowance (WDA) approach. For a solar installation costing £300,000 and a business paying 25% corporation tax, the AIA saves £75,000 in tax in the first year — reducing the effective cost of the installation to £225,000.

Key AIA Rules for Factory Solar

Rule Detail
Annual limit £1,000,000 per annum (confirmed for 2026-27)
Eligible entities UK companies, partnerships, sole traders — most commercial businesses qualify
Solar panels eligible? Yes — panels, inverters, mounting, cabling, monitoring systems all qualify as plant and machinery
Timing Deduction taken in the tax year in which expenditure is incurred (typically the year installation is completed)
Tax saving (25% CT rate) 25% of eligible expenditure; a £200,000 installation saves £50,000 in corporation tax
Planning consideration If multiple capital investments are planned, consider staging to maximise AIA use in each tax year

Note: The AIA is a UK government tax relief. Always confirm eligibility and optimal timing with your accountant or tax adviser. This article provides general information only and is not tax advice.

IETF Phase 4: Applications Open

IETF Phase 4 Application Window: Open Spring 2026

The Industrial Energy Transformation Fund (IETF) Phase 4 application window is currently open as of April 2026. Eligible manufacturers can apply for capital grants of up to 50% of eligible project costs for energy efficiency and decarbonisation projects. Application deadline to be confirmed — check DESNZ for current guidance.

The IETF is the UK government's primary capital grant programme for energy-intensive manufacturing businesses seeking to reduce their energy consumption and carbon emissions. Phase 4 continues the programme structure established in earlier phases, with grants available for qualifying capital projects including solar PV installation.

IETF Phase 4 Eligibility Criteria

  • Energy-intensive manufacturer — IETF is targeted at businesses where energy costs represent a significant proportion of total production costs. There is no fixed threshold, but applicants must demonstrate energy-intensive activity.
  • UK-based manufacturing — the funded project must be at a UK manufacturing facility. The business must be trading in the UK and intend to continue doing so for at least the grant term.
  • Minimum project size — Phase 4 typically requires a minimum eligible project cost of £100,000 to qualify for a grant. Projects below this threshold are unlikely to meet the administrative cost-benefit threshold for IETF.
  • Additionality — the IETF requires that the grant is necessary for the project to proceed on the planned timeline. Projects that would proceed anyway without the grant are unlikely to score well on additionality criteria.
  • State aid compliance — IETF grants are provided under the UK Subsidy Control Act 2022. Businesses that have received other public subsidies may have cumulative limits to manage.

Grant Percentages and Eligible Activities

Activity Type Max Grant % Example
Energy efficiency improvement Up to 30% LED replacement, compressed air efficiency, heat recovery
Deep decarbonisation technology Up to 50% Solar PV, electrification of heat processes, hydrogen-ready equipment
Feasibility studies Up to 50% Detailed energy audits, decarbonisation roadmap development

Solar PV is specifically listed as an eligible activity under Phase 4's deep decarbonisation technology category, qualifying for up to 50% grant funding. For a £300,000 solar installation, a successful IETF Phase 4 application could contribute up to £150,000 in grant funding — dramatically improving the financial case and potentially halving the payback period.

The IETF is competitive and oversubscribed. It is strongly advisable to engage an experienced IETF grant consultant to prepare your application — success rates for professionally prepared applications are significantly higher than self-prepared submissions. Allow 8–16 weeks from application to grant decision.

ESOS Phase 4: December 2027 Deadline Approaching

ESOS Phase 4 Compliance Deadline: 5 December 2027

UK businesses that qualify for ESOS (Energy Savings Opportunity Scheme) must complete their Phase 4 energy audit and submit their compliance notification to the Environment Agency by 5 December 2027. With only 20 months remaining, businesses should be engaging ESOS Lead Assessors and beginning their audit process now.

Who Qualifies for ESOS Phase 4?

An organisation qualifies for ESOS if it meets any of the following criteria:

  • Has 250 or more employees; or
  • Has an annual turnover exceeding £44 million AND a balance sheet exceeding £38 million; or
  • Is a UK subsidiary of a qualifying company within a corporate group

How Solar Satisfies ESOS Obligations

ESOS requires qualifying organisations to conduct audits of their energy use and identify energy saving opportunities — it does not mandate implementation. However, Phase 4 introduced a "Significant Energy Savings Opportunities" requirement: businesses must identify and explain in their ESOS report at least one significant energy saving opportunity, or explain why none exist.

Businesses that have already installed solar panels can reference the solar installation as evidence of energy saving action taken. The ESOS report should include: total generation data from the solar monitoring system; the kWh displaced from grid electricity; the associated CO2 reduction; and the financial saving achieved. This demonstrates compliance with the spirit of ESOS — identifying and implementing energy savings — and typically satisfies ESOS Lead Assessors reviewing the submission.

For more detail on ESOS compliance, see our dedicated guide: ESOS Phase 4 Solar Compliance Guide.

Smart Export Guarantee: Current Rates Spring 2026

The Smart Export Guarantee (SEG) requires licensed electricity suppliers with over 150,000 domestic customers to offer export tariffs to eligible small-scale generators. For commercial and industrial systems, the process and rates differ from domestic SEG applications.

Supplier Tariff Name Rate (Spring 2026) Commercial Availability
Octopus Energy Outgoing Octopus 5.0–6.0p/kWh Yes — commercial systems up to 5MW eligible; contact for large systems
E.ON Next Export Exclusive 4.0–5.0p/kWh Available; rates for large commercial may be individually negotiated
British Gas Solar Export 3.5–4.5p/kWh Available; commercial applications processed separately
EDF Energy Export tariff 3.5–5.0p/kWh Available; large commercial negotiated individually
Scottish Power Export tariff 3.0–4.0p/kWh Available; contact commercial team for large systems

Note: SEG rates change frequently. The figures above are indicative for Spring 2026 based on published tariff data. Always check current rates directly with your electricity supplier. For systems over 50kW (G99 applications), commercial SEG arrangements may differ from published domestic rates.

G99 and SEG: Important Note

Factory solar systems over 50kW require a G99 grid connection agreement with your DNO. You must have a G99 Agreement in place before you can register for SEG export payments. Most SEG suppliers require a copy of your G99 Agreement and an MCS certificate (or equivalent) as part of the registration process.

EPC Band C Deadline: April 2027 for New Commercial Leases

Action Required: April 2027 Deadline

From April 2027, it will be unlawful for landlords in England and Wales to let commercial property on a new lease if the building has an EPC rating below Band C. Buildings currently at Band D or below must be improved before they can be marketed for new leases.

The Minimum Energy Efficiency Standards (MEES) for commercial buildings are being progressively tightened. The current minimum for new commercial leases is EPC Band E. From April 2027, this rises to Band C — a significant step up that affects a large proportion of older UK commercial and industrial properties.

How Solar Contributes to EPC Improvement

EPC ratings for commercial buildings are calculated using the Simplified Building Energy Model (SBEM), which assesses the building's estimated energy performance. Solar panels reduce the building's estimated net energy consumption by generating electricity on-site, which improves the EPC score.

The EPC improvement from solar varies by building type, size and existing rating, but in general:

  • A building at Band D may improve to Band C with a solar system sized to offset 30–40% of annual energy use.
  • A building at Band E typically requires solar plus one or two other measures (LED lighting, roof insulation) to reach Band C.
  • A new EPC must be produced after solar installation to reflect the improvement — your installer should be able to advise on whether a new assessment is needed.

For commercial landlords with industrial tenants, the April 2027 deadline is 12 months away. Commissioning an EPC assessment now, followed by solar installation (total project timeline typically 4–6 months), leaves a comfortable margin before the deadline.

UK ETS Carbon Price: Implications for Energy-Intensive Manufacturers

The UK Emissions Trading Scheme (UK ETS) is a cap-and-trade carbon pricing mechanism that applies to large energy-intensive installations, including power stations and certain manufacturing processes. The UK ETS carbon price in Spring 2026 is approximately £38–45/tonne CO2.

Most factory solar decisions are not directly driven by the UK ETS, as the scheme applies to electricity generators rather than electricity consumers. However, the UK ETS has two indirect effects on factory solar economics:

1. ETS Adds to Electricity Prices

Gas-fired power stations pay UK ETS allowances on their CO2 emissions. These costs are passed through to electricity buyers in the wholesale market. At £40/tonne CO2 and a gas plant efficiency of approximately 50%, the UK ETS adds approximately 1.5–2p/kWh to wholesale electricity prices. This contributes to the elevated electricity prices that make solar attractive.

2. CBAM Applies to Certain EU-Exported Products

The EU Carbon Border Adjustment Mechanism (CBAM) applies to steel, aluminium, cement, fertilisers, electricity and hydrogen exported to the EU. From 2026, exporters of these products to the EU must pay a CBAM charge reflecting the carbon intensity of production. Reducing the Scope 2 carbon intensity of production (through solar) directly reduces CBAM liability for affected manufacturers. For steel fabricators and aluminium processors exporting to the EU, this is an increasingly material financial consideration.

DNO Connection Timelines: Regional Update Spring 2026

G99 grid connection applications — required for factory solar systems over 50kW — are processed by the relevant Distribution Network Operator (DNO). Processing times have improved modestly compared to 2024 peak congestion, but remain variable by region. The following table shows current (Spring 2026) indicative G99 processing timelines.

DNO Region Typical G99 Processing Time Comments
National Grid / UK Power Networks South East, East Anglia 14–20 weeks High constraint area; network reinforcement more common
Western Power Distribution (now National Grid) South West, Midlands, South Wales 8–14 weeks Improving; Bristol area longer than average
Northern Powergrid North East England, Yorkshire 8–12 weeks Generally improving; some congestion in Teesside industrial areas
Electricity North West North West England 10–16 weeks Greater Manchester industrial zones seeing longer waits
SP Energy Networks Scotland, North Wales 10–18 weeks Variable by area; rural areas often longer

Tips for Accelerating G99 Applications

  • Submit early: The G99 application clock only starts when the DNO accepts your application. Submit as early as possible in the project — ideally immediately after the site survey is completed, before finalising panel count and inverter selection.
  • Use a specialist installer: Experienced installers know the DNO application process, can prepare technically accurate submissions first time, and have established relationships with DNO connection engineers. Poor-quality applications are returned with queries, adding weeks to processing time.
  • Have your site electrical details ready: DNO applications require details of your existing electrical infrastructure, main switch fuse (MSF) rating, and existing metering arrangement. Gather these before submitting.
  • Budget for reinforcement: Ask your installer to check network headroom at your site before committing to a project. If headroom is tight, factor in potential reinforcement costs and delays from the outset.

Net Zero Supply Chain Requirements: Automotive Sector Update

The UK automotive sector's supply chain sustainability requirements have accelerated materially in 2025–2026, driven by OEM commitments to Net Zero supply chains and the EU's Corporate Sustainability Reporting Directive (CSRD) — which requires European vehicle manufacturers to report Scope 3 emissions from UK suppliers.

JLR (Jaguar Land Rover) Supplier Requirements

JLR has committed to reaching net zero across its entire supply chain by 2039. From 2026, JLR's supplier questionnaires now require Tier 1 and selected Tier 2 suppliers to provide verified Scope 1 and Scope 2 emissions data, and to demonstrate a credible decarbonisation plan. Solar PV installation — with verified generation data — directly satisfies the Scope 2 evidence requirement and demonstrates active decarbonisation action.

Nissan Manufacturing UK Supply Chain

Nissan's Sunderland plant (producing the Nissan Leaf and Ariya) has committed to operating on 100% renewable electricity by 2028, and is extending this requirement to key Tier 1 suppliers from 2027. Suppliers are being asked to demonstrate renewable electricity use through one of three mechanisms: direct solar generation, renewable energy certificates (RECs), or a green electricity tariff. On-site solar generation is the most commercially attractive and evidentially robust of these options.

Toyota UK Supply Chain

Toyota's Burnaston and Deeside plants have issued supplier sustainability guidance requiring Tier 1 suppliers to have completed a carbon footprint assessment and identified their largest emission sources by December 2026. Suppliers with purchased electricity as a significant Scope 2 source are being encouraged to invest in on-site renewable generation. Solar PV is specifically cited in Toyota's supplier guidance as a preferred route to Scope 2 reduction.

For UK automotive suppliers, the combination of supply chain requirements from multiple OEMs and the financial case for solar on its own merits creates a compelling and multi-dimensional argument for investment. The supply chain compliance value of solar can be quantified in terms of contract retention and preferred supplier status — factors that can dwarf the electricity savings in commercial significance.

Frequently Asked Questions

Is the Annual Investment Allowance still available in 2026?
Yes. The Annual Investment Allowance (AIA) remains at £1 million for the 2026-27 tax year, confirmed in the Spring 2026 Budget. Solar panels installed on commercial properties qualify as plant and machinery and are eligible for 100% first-year deduction under AIA. This reduces the effective after-tax cost of solar installation by 25% for a 25% corporation tax payer — e.g. a £200,000 system costs effectively £150,000 after tax. Always confirm with your accountant.
When is the ESOS Phase 4 deadline?
The ESOS Phase 4 compliance deadline is 5 December 2027. Qualifying organisations (250+ employees, or turnover over £44M and balance sheet over £38M) must complete an energy audit conducted by a qualified Lead Assessor and submit a compliance notification to the Environment Agency by this date. With 20 months remaining, businesses should engage an ESOS Lead Assessor now to begin the assessment process.
How do I apply for IETF Phase 4?
IETF Phase 4 applications are submitted through the DESNZ online portal. Applications require a detailed project description, evidence of energy-intensive manufacturing status, and cost-benefit analysis including energy savings projections. It is strongly recommended to engage an experienced grant consultant — IETF applications are complex and competitive, with professional preparation significantly improving success rates. Contact us and we can introduce you to IETF-experienced advisers who have delivered successful Phase 3 and Phase 4 applications.
What are current SEG rates in Spring 2026?
Current Smart Export Guarantee (SEG) rates in Spring 2026 range from 3p/kWh to 6p/kWh depending on the supplier and tariff. Octopus Energy's Outgoing Octopus tariff currently offers approximately 5–6p/kWh. E.ON's Export Exclusive pays approximately 4–5p/kWh. British Gas pays approximately 3.5–4.5p/kWh. Commercial sites over 50kW typically require individual negotiation — contact your electricity supplier's commercial team directly. Always confirm current rates as they change regularly.
How does the EPC Band C deadline affect commercial property owners?
From April 2027, commercial properties in England and Wales must achieve a minimum EPC Band C rating to be let on a new lease. Properties below Band C will be unlettable for new leases until improved. Existing leases are not immediately affected, but renewals may trigger the requirement. Solar panels can improve EPC ratings by 1–2 bands depending on system size and building type. If your industrial or commercial property is currently Band D or below, an EPC assessment followed by solar installation is one of the most effective routes to compliance before the deadline. See our guide: EPC Commercial Building Solar Upgrade.

Ready to Cut Your Factory Energy Costs?

Get a free, no-obligation solar assessment for your factory or warehouse.

Get Free Assessment