What inputs a factory solar ROI model needs
A credible factory solar ROI model is not a simple payback calculation. Simple payback — total capital cost divided by annual savings — ignores the time value of money, tax timing, and the compounding effect of tariff escalation over a 25-year asset life. A proper model is a discounted cash flow (DCF) analysis that captures every relevant cost and benefit stream across the system's operating life.
The following are the minimum inputs required to build a model that will support an investment decision:
Capital cost (ex-VAT)
The fully installed cost of the system including panels, inverters, mounting, electrical works, DNO application, metering, and commissioning. In 2026, UK factory solar typically costs £600–£850 per kWp installed, depending on system size, roof type, and complexity. Larger systems (500 kWp and above) attract lower per-kWp pricing due to economies of scale. Always obtain at least three competitive quotes and ensure each quote covers an identical scope.
Annual generation (kWh)
Derived from a P50 yield estimate produced using industry-standard tools such as PVsyst, using site-specific irradiance data (typically from PVGIS or Meteonorm), a panel degradation curve (typically 0.3–0.5% per year for modern monocrystalline panels), and a performance ratio (PR) of 0.78–0.85. In southern England, expect approximately 900–950 kWh/kWp/year. In Scotland or the north-west of England, 820–870 kWh/kWp/year. Verify that the yield estimate reflects the actual roof orientation and pitch of your building.
Self-consumption rate (%)
The proportion of solar generation consumed on-site rather than exported. This is the single most consequential variable in the model (discussed in detail in the next section). Typical range for UK factories: 50–85% depending on operating pattern. Requires analysis of your half-hourly AMR data against a modelled generation profile.
Current electricity unit rate (p/kWh)
The blended average unit rate on your current electricity contract, inclusive of all pass-through costs (distribution, transmission, levies) but exclusive of the standing charge. In 2026, UK industrial electricity unit rates are typically 24–33p/kWh depending on contract vintage, supply voltage, and location. This is the displacement value per unit of self-consumed generation.
Export tariff (p/kWh)
The rate earned on electricity exported to the grid. Under Smart Export Guarantee (SEG), this is market-driven and currently 3–8p/kWh for most industrial sites. Some sites have zero export conditions imposed by the DNO, in which case exported generation earns nothing and must be curtailed or stored. Power Purchase Agreements (PPAs) may offer a different export structure.
Annual tariff escalation assumption (%)
The assumed annual real-terms increase in electricity prices over the 25-year model period. This is an inherently uncertain input that should always be scenario-tested rather than hard-coded as a single figure. Central range: 2–3% real per annum.
Annual O&M cost
Typically £5–£10 per kWp per year for a commercial rooftop system, covering annual inspection and cleaning, inverter monitoring, and reactive maintenance budget. Inverter replacement at year 10–12 should also be modelled as a capital event (approximately £15,000–£30,000 for a 300–500 kWp system).
Discount rate (%)
Your organisation's weighted average cost of capital (WACC) or minimum acceptable rate of return. For UK manufacturers in 2026, a post-tax discount rate of 8–12% is typical. The choice of discount rate significantly affects the NPV calculation and should reflect your actual cost of capital, not an arbitrary figure.
Corporation tax rate and capital allowance treatment
The current UK main corporation tax rate is 25% (for companies with profits above £250,000). Full Expensing (100% first-year allowance for qualifying plant and machinery) materially improves the post-tax cash flow profile. This input is often omitted from installer-provided calculations, causing them to understate returns.
Self-consumption rate — the most important variable
If you can only model one variable with precision, make it the self-consumption rate. No other single input has as large an effect on your ROI calculation. Here is the arithmetic: a unit of solar electricity self-consumed displaces a unit of grid electricity at 28–32p/kWh. A unit exported earns approximately 5p/kWh under SEG. The value difference is roughly 25p per unit — and for a 300 kWp system generating 270,000 kWh per year, a 10 percentage-point change in self-consumption rate (from 60% to 70%) is worth approximately £6,750 per year.
Over a 25-year asset life with 2.5% annual tariff escalation, that 10-point swing in self-consumption rate equates to approximately £235,000 in additional total value — more than the total capital cost of many factory solar installations. Getting this variable right matters enormously.
Typical Self-Consumption Rates by Factory Operating Pattern
| Operating Pattern | Typical Self-Consumption | Notes |
|---|---|---|
| 24/7 continuous production | 80–90% | High overnight and weekend loads consume most generation |
| Double shift (06:00–22:00) | 70–80% | Good overlap with solar generation hours |
| Standard day shift (08:00–18:00) | 55–70% | Good weekday match; summer weekend surplus common |
| Monday–Friday only, day shift | 45–60% | Weekend surplus reduces self-consumption materially |
| Seasonal or intermittent production | 30–50% | Significant mismatch; battery storage should be evaluated |
The only reliable way to estimate self-consumption rate is to cross-reference your half-hourly AMR (Automatic Meter Reading) data with a modelled solar generation profile for the same period. Your electricity supplier or DNO can provide half-hourly consumption data for any HH-metered site. If your site is not HH-metered, interval data from a smart meter will suffice, though at 30-minute resolution rather than half-hourly.
Beware of self-consumption estimates provided by installers without reference to your actual consumption data. A common error is to assume that because the factory's annual consumption (say, 1,000,000 kWh) greatly exceeds the annual generation (say, 250,000 kWh), self-consumption will be 100%. This ignores temporal mismatch: solar generates mostly between 08:00 and 18:00 on clear days, and a factory that consumes heavily overnight or at weekends may not be able to use much of that generation regardless of annual totals.
Modelling the tariff escalation assumption
Electricity price forecasting is one of the most contested areas of energy economics. UK industrial electricity prices have been volatile: the wholesale spike of 2021–2022 pushed industrial unit rates above 60p/kWh on some spot-exposed contracts before reverting to 24–32p/kWh by 2025–2026. Any model that anchors its long-term escalation assumption to the 2021–2022 peak is misleading; any model that assumes zero escalation from current levels is equally problematic.
The appropriate approach is to use a central case based on credible published forecasts and to scenario-test it. NESO's Future Energy Scenarios (FES) and DESNZ's updated energy price projections provide the most authoritative long-run guidance. The FES 2024 central scenario implies real-terms electricity price growth of approximately 1.5–2.5% per year from 2026 to 2035, moderating thereafter as offshore wind and interconnection capacity increases.
Recommended Tariff Escalation Assumptions by Scenario
A critical point: the tariff escalation assumption has very different effects in early and late years of the model. Because of discounting, year 20–25 cash flows contribute relatively little to NPV regardless of assumed escalation. The escalation assumption matters most in years 5–15, where cash flows are large enough to be material and discounting has not yet eroded their present value significantly. Sensitivity testing should focus on this middle period.
Full Expensing and AIA — how tax relief reshapes payback
The UK's capital allowance regime is one of the most favourable in the G7 for capital-intensive investments like solar. Two mechanisms are currently available to UK companies investing in factory solar: Full Expensing and the Annual Investment Allowance (AIA).
Full Expensing was made permanent in the Autumn Statement 2023 (effective from April 2023). It allows companies to deduct 100% of qualifying plant and machinery expenditure against taxable profits in the year of investment. Solar panels, inverters, battery storage, and associated electrical equipment all qualify as plant and machinery. For a company paying the 25% corporation tax rate, a £600,000 solar installation delivers a £150,000 tax deduction — in the same year as the capital expenditure. This effectively reduces the net capital outlay to £450,000, compressing the payback period by roughly 25%.
Annual Investment Allowance (AIA) achieves the same 100% first-year deduction but is subject to an annual limit (currently £1 million per year for most companies). For solar systems below £1 million in capital cost, AIA delivers the same benefit as Full Expensing. For larger projects, Full Expensing covers the excess above the AIA limit without restriction.
Illustrative Tax Relief Impact: 400 kWp Factory Solar System
Without Full Expensing (pre-2023)
Capital cost: £280,000
18% writing-down allowance (WDA) pool
Year 1 deduction: £50,400 (18% of £280,000)
Year 1 tax saving: £12,600 (25% x £50,400)
Full tax benefit spread over 10+ years
With Full Expensing (2026)
Capital cost: £280,000
100% first-year deduction
Year 1 deduction: £280,000
Year 1 tax saving: £70,000 (25% x £280,000)
Entire tax benefit received in year of investment
The practical effect is to advance approximately £57,000 in tax relief from future years to year one — equivalent to reducing the effective capital cost by over 20%. For a company with taxable profits sufficient to absorb the deduction in year one, this is a significant and guaranteed benefit that should always be included in the ROI model.
One caveat: Full Expensing and AIA require the company to have taxable profits in the year of the claim. Loss-making businesses cannot claim the allowance in year one (though losses can be carried forward). If your company is currently loss-making or has marginal profitability, the tax relief timing in your model must reflect this reality rather than assuming year-one relief.
What IRR and NPV actually tell you (and don't)
Simple payback period is useful for a first-pass filter, but it is not an adequate basis for a capital investment decision. Two metrics — Internal Rate of Return (IRR) and Net Present Value (NPV) — provide a more complete picture, but both are frequently misunderstood or misapplied.
Internal Rate of Return (IRR) is the discount rate at which the NPV of the investment's cash flows equals zero. It represents the annualised post-tax return on the capital invested over the full life of the asset. For factory solar in 2026 under base-case assumptions, post-tax IRRs of 12–22% are typical for energy-intensive sites — well above the 10–15% hurdle rates applied by most UK manufacturers. A higher IRR means the investment is more attractive relative to competing uses of capital.
Net Present Value (NPV) is the present value of all future cash flows minus the initial capital cost, discounted at your required rate of return (typically WACC). A positive NPV means the investment creates value above your hurdle rate. The NPV figure gives you the absolute monetary value created — which IRR does not. A project with a 25% IRR on a £10,000 investment creates less value than a project with a 15% IRR on a £500,000 investment.
IRR Limitations to Be Aware Of
- IRR assumes cash flows are reinvested at the IRR rate — unrealistic for high-IRR projects. Modified IRR (MIRR) using a realistic reinvestment rate is more accurate.
- IRR cannot distinguish between a large positive-NPV project and a small one — always present NPV alongside IRR to show absolute value creation.
- NPV is highly sensitive to the discount rate used. Always show NPV at your WACC and also at WACC +3% as a sensitivity test.
- Neither IRR nor NPV capture non-financial value: carbon reduction, ESG reporting improvement, CBAM liability reduction, and supply chain resilience.
For most UK factory solar investment committees, the most persuasive presentation is: simple payback (for intuition), post-tax IRR compared to WACC (for return adequacy), and NPV at WACC (for absolute value creation) — all shown across three scenarios.
Three-scenario model: pessimistic, base, optimistic
Presenting a single-scenario ROI model to a board or finance committee is an invitation to challenge the assumptions. A three-scenario model — pessimistic, base, and optimistic — demonstrates analytical rigour and makes the investment case more robust by explicitly addressing downside risk.
| Assumption | Pessimistic | Base Case | Optimistic |
|---|---|---|---|
| System size | 300 kWp | 300 kWp | 300 kWp |
| Capital cost per kWp | £850/kWp | £720/kWp | £640/kWp |
| Self-consumption rate | 50% | 65% | 80% |
| Current unit rate | 24p/kWh | 28p/kWh | 32p/kWh |
| Tariff escalation (real) | 0% p.a. | 2.5% p.a. | 5% p.a. |
| Annual yield (kWh/kWp) | 840 | 890 | 940 |
| Implied simple payback | 8.1 years | 4.9 years | 3.2 years |
| Post-tax IRR (25yr, FEXP) | 9.8% | 17.4% | 26.1% |
| NPV at 10% discount rate | -£18,000 | +£142,000 | +£348,000 |
The pessimistic scenario — with a negative NPV at 10% discount rate — illustrates that factory solar is not unconditionally attractive. Sites with low self-consumption, low energy unit rates, and no tariff escalation may not clear a 10% hurdle rate. However, note that even the pessimistic scenario has a post-tax IRR of 9.8% — not far below the hurdle rate, and the model still returns the capital invested with a modest loss in present-value terms. The base case, which reflects realistic conditions for a typical energy-intensive UK factory, delivers a convincing 17.4% IRR and £142,000 of NPV on a £216,000 capital outlay.
Two additional scenarios worth running: a carbon price scenario (if your company uses an internal carbon price in investment decisions) and a PPA scenario (if you are considering funding the system through a Power Purchase Agreement rather than direct capital expenditure).
When to update your model (at commissioning, year 2, year 5)
A solar ROI model is not a one-time document produced before investment and filed away. The assumptions embedded in the pre-investment model need to be tested against actual performance data and updated at regular intervals. This is not bureaucratic — it is essential for detecting underperformance early and for validating the investment thesis for future projects.
At commissioning (month 1)
Record the final installed capital cost (which may differ from the quote due to variations) and confirm the as-built system specification. Verify that monitoring data is flowing correctly from the generation meter and inverters. Establish a baseline half-hourly consumption profile for comparison with generation data.
At end of year 1 (first full year)
Compare actual annual generation against the P50 yield estimate. A shortfall of more than 5% warrants investigation — possible causes include module soiling, shading from new obstructions, inverter underperformance, or wiring losses not captured in the design model. Compare actual self-consumption rate against the modelled assumption. Update the 25-year projection with actual year-1 performance data.
At year 2
By year 2 you have a full year's actual data unaffected by commissioning teething issues. This is the first reliable basis for a performance comparison. Update the electricity unit rate in your model to reflect your current contract. Review whether your operating pattern has changed materially (shift changes, new production lines, plant disposals) and update the self-consumption assumption if so.
At year 5
Year 5 is a natural strategic review point. Your current electricity contract will likely have been renewed at least once, giving you a real-world data point on tariff escalation to compare against your model assumption. You should also review the degradation rate against the manufacturer's guarantee: a loss of more than 3% in five years from a modern panel warrants a warranty claim. If you have battery storage, year 5 is when capacity fade starts to become measurable — verify that the battery management system is reporting state of health accurately.
The model updates at years 2 and 5 also serve a second purpose: they provide the empirical evidence base for your next solar investment decision. If you are considering a second roof, a ground-mount, or battery storage addition, the actual performance data from your first system is vastly more valuable than any installer's generic assumption set.
Using the Solar Panels for Factories calculator
The Solar Panels for Factories online calculator is designed to give UK manufacturers a rapid first-pass ROI estimate based on your specific inputs. It implements the methodology described in this guide: a DCF model with customisable self-consumption rate, tariff escalation, and discount rate, with Full Expensing applied automatically for companies paying corporation tax.
The calculator is not a substitute for a detailed site-specific model — it does not incorporate your half-hourly AMR data or the specific yield estimate for your roof. But it is a robust screening tool that will tell you whether a detailed analysis is warranted, and it produces outputs (payback, IRR, NPV) in a format suitable for an initial internal discussion.
To use the calculator effectively, you will need:
- Your factory's annual electricity consumption in kWh (from your bills or meter data)
- Your current all-in electricity unit rate in pence per kWh
- An estimate of your roof area available for solar (or a target system size in kWp)
- Your operating pattern (days and hours per week)
- Whether you pay UK corporation tax (for Full Expensing calculation)
The calculator will produce a base-case payback period, post-tax IRR, and NPV. If the results suggest a payback below 6 years and an IRR above 12%, the investment is likely viable and warrants a full site survey and detailed proposal. If the results suggest a payback above 8 years, this guide's section on self-consumption rate and tariff escalation will help you understand which assumptions are driving that result and whether a different system design might improve the economics.
Access the Factory Solar ROI Calculator
Run your own three-scenario ROI model with our free calculator. No email required for the initial estimate.
Open the CalculatorFrequently Asked Questions
What is a realistic payback period for factory solar in the UK in 2026?
What is the most important variable in a factory solar ROI model?
How does Full Expensing affect factory solar ROI?
What tariff escalation rate should I use in my solar model?
What IRR should a factory solar project achieve to be worth proceeding?
Trusted Solar Installers Across the UK
We work with a network of MCS-certified regional installers. If you need a recommendation outside our coverage area, these are the firms we trust:
- ALPS Electrical — MCS-certified solar installer — Teesside & North East England
- Midland Solar — Commercial & industrial solar installer — West Midlands
- EC Eco Energy — UK-wide commercial solar & renewables installer
- Sola UK — Solar panels & battery storage specialist — Hertfordshire
- Carbon Legacy — Solar & green energy solutions — East Midlands
- Premier Electrical Renewables — Solar, batteries & EV chargers — South Yorkshire